OSHA requires that process equipment and materials meet applicable design specifications before installation. The QA element of MI addresses receiving inspection, material traceability, mill certifications, and the controls needed to ensure that a replacement valve, fitting, or gasket installed in a covered process matches the specification it was supposed to replace. Counterfeit or substandard materials in process piping have caused serious incidents. These letters address what the QA program must include, the role of receiving inspection, and how to handle materials purchased outside normal procurement channels.
What OSHA Has Said
⚡ Key Compliance Takeaway
Receiving inspection is not optional. Every replacement part for a covered process needs specification verification and documentation before installation including emergency procurements. Trusting the supplier is not a QA program; verifying the mill cert and checking the marking is.