29 CFR 1910.119(j)(6) is the quality assurance part of mechanical integrity. In construction of new plants and equipment, the employer must assure that equipment as it is fabricated is suitable for the process application (j)(6)(i); perform appropriate checks and inspections to assure it is installed properly and consistent with design specifications and the manufacturer's instructions (j)(6)(ii); and assure that maintenance materials, spare parts, and equipment are suitable for the process application (j)(6)(iii). OSHA has few letters devoted to (j)(6), but the ones below show how it applies.

What OSHA Has Said

Feb 1, 2010
Blast-resistant structures: design, siting, and resolving deficiencies
In a letter to a U.S. Senator about refinery structures exposed to explosion hazards, OSHA said blast-resistant structures must be designed and maintained to RAGAGEP. Deficiencies found in a facility siting evaluation must be resolved and documented under (e)(5), and changes to structures go through MOC. Where a structure contains equipment covered by mechanical integrity, MI applies: new equipment must be fabricated to be suitable for its application under (j)(6)(i), and checks and inspections must confirm it is installed properly and consistent with design specifications and manufacturer's instructions under (j)(6)(ii).
Read OSHA Letter ↗
Dec 4, 2012
Reassembling cylinder valves is an MI activity
A chlorine repackager asked whether disassembling, inspecting, reassembling, and testing valves on returned cylinders and ton containers falls under mechanical integrity. OSHA said yes, including the documentation requirement in (j)(4)(iv), once the cylinder or container is connected to a covered process. A one-ton chlorine container is itself a covered process because it holds more than the 1,500-pound threshold, so its valve and appurtenances must be maintained under (j).
Read OSHA Letter ↗
Mar 5, 1998
Missing material and weld records on existing vessels
When no documentation exists for an existing vessel's materials of construction, welding procedures, or radiographic testing, OSHA said it is appropriate to assume the lowest values (such as the lowest weld joint efficiency and allowable stress) in an engineering analysis done to current codes to confirm the vessel is suitable for service.
Read OSHA Letter ↗

⚡ Key Compliance Takeaway

Build quality assurance into procurement and turnover: verify materials and fabrication records for new equipment, inspect installation against the design and the vendor's instructions before startup, and control spare parts so the wrong material can't end up in a covered process. For older equipment with missing records, document a conservative engineering analysis rather than assuming the original spec.